Government has secured parliamentary approval for another $24.7 billion for the gas-to-energy project at Wales, West Bank Demerara, to complete Phase 1 and purchase turbines for Phase 2.
Prime Minister Brigadier (Ret’d) Mark Phillips told the Parliamentary Committee of Supply on Monday that all four turbines under the first phase are expected to be operational by the end of 2027.
The project is intended to supply an additional 300 megawatts of electricity and fulfil government’s commitment to halve electricity costs.
“We made a commitment to the people of Guyana that they will get 300 additional megawatts of power at 50 per cent of what they are paying for now,” Phillips said.
The Prime Minister also disclosed that the project’s overall cost has been revised to US$956 million, compared with the previous US$759 million.
He explained that the contractor sought an additional US$200 million, which government agreed to pay. Of that amount, US$130 million has already been paid.
Phillips said the additional expenditure was necessary to keep construction moving and avoid a suspension of works or litigation.